Post Contract

Variation Order Claim
Don't key in "Rate" in "-" Negative value. If want to make the amount in "-" manually, please key in Qty in "-".
Sun, 19 Dec, 2021 at 1:50 PM
Preparation of Variation Order IMPORTANT NOTES
1. If user would like to input a negative VO, the negative amount will need to be input under quantity (ie: -100). DO NOT key in negative amount at the Rate...
Thu, 9 Dec, 2021 at 5:20 PM
Claim Verification
1) User unable to access to verify claim?  BS: User will need to check whether they have access to BuildSpace Pro rights or not at "Manage Users"...
Fri, 7 Jan, 2022 at 9:31 AM
Post Contract Verification
1) Why can't I seethe claims or any other documents pending for my verification? BS: Please check with the project admin whether you are assigned as th...
Fri, 7 Jan, 2022 at 9:33 AM
Some information went missing in my Claim Certificate
Check on the claim certificate version and make sure to select the correct "view this revision"
Thu, 20 Oct, 2022 at 11:44 AM
Amount not tally in claim
1. If the amount is 100% in claim, please key in using percentage (100%)  instead of quantity or amount.
Wed, 3 Jan, 2024 at 6:17 PM
Missing "Action" button at Project Dashboard
This issue occurs because the project is currently assigned to the Group Contract Division (GCD). Kindly remove the GCD assignment from the project, af...
Tue, 4 Nov, 2025 at 5:00 PM