Don't key in "Rate" in "-" Negative value. If want to make the amount in "-" manually, please key in Qty in "-".
Sun, 19 Dec, 2021 at 1:50 PM
1. If user would like to input a negative VO, the negative amount will need to be input under quantity (ie: -100). DO NOT key in negative amount at the Rate...
Thu, 9 Dec, 2021 at 5:20 PM
1) User unable to access to verify claim? BS: User will need to check whether they have access to BuildSpace Pro rights or not at "Manage Users"...
Fri, 7 Jan, 2022 at 9:31 AM
1) Why can't I seethe claims or any other documents pending for my verification? BS: Please check with the project admin whether you are assigned as th...
Fri, 7 Jan, 2022 at 9:33 AM
Check on the claim certificate version and make sure to select the correct "view this revision"
Thu, 20 Oct, 2022 at 11:44 AM
1. If the amount is 100% in claim, please key in using percentage (100%) instead of quantity or amount.
Wed, 3 Jan, 2024 at 6:17 PM